Song Hau 1 thermal power plant is closely operated in accordance with the new progress milestone

Song Hau 1 thermal power plant is closely operated in accordance with the new progress milestone

Information from Song Hau 1 Petroleum Power Project Management Board (under Vietnam Oil and Gas Group - PVN) said: As of March 15, 2021, the construction of Song Hau 1 thermal power project (TPP – 1200 MW) reaches a cumulative progress about 95.78% including construction of 98.12%, design of 99.91%, procurement of 99.91% and test of 74.85%.