Coal combustion for the first time in Unit N#2 boiler of Vinh Tan 4 TPP
08:40 | 29/06/2017
According to the information from GENCO 3, at 12:20 on June 27, 2017, coal burning for the first time at Unit#2 (600MW) of Vinh Tan 4 thermal power plant (TPP) was successfully implemented This is an important milestone as a basis for following testing steps with an aim to commercial operating Unit#2 at the end of 2017.
Unit No. 2 of Vung Ang 1 Thermal Power Plant has been officially put into commercial operation
23:15 | 14/05/2015
On May 12, Limama EPC general contractor handed over the Unit No. 2 of Vung Ang 1 Thermal Power Plant (TPP) to the Petroietnam (PVN) investor for commercial operation.
Unit 1 of the Mong Duong II BOT Thermal Power Plant (TPP) as been put into operation
09:22 | 27/03/2015
Unit 1 of 1120 MW BOT Mong Duong 2 TPP has been put into operation