Coal combustion for the first time in Unit N#2 boiler of Vinh Tan 4 TPP
08:40 | 29/06/2017
Previously, flue gas treating systems as flue gas desulfurization (FGD) by sea water, electrostatic precipitator (ESP) of Vinh Tan 4 TPP were put into operation right from coal combustion for guaranteeing clean environment during testing process as well as when the TPP will be officially put into operation (without a column of back smock).
Vinh Tan 4 TPP is one of the key projects invested by EVN. This is the first in Vietnam large coal fired TPP with supercritical steam parameters. The project includes two units by a capacity of 600 MW each (2x600 MW).
As planed, the first unit of the plant will be put into operation after 46 month development (at the end of 2017), the second unit expects to be in operation after the first one for 6 months (in the second quarter of 2018). The plant will be connected with national power system by power grid of 500 kV.
The project EPC general contractor is a consortium of DOOSAN (S. Korea), MITSUBISHI (Japan), PECC2 and PACIFIC (Vietnam). The PECC2 and foreign TRACTEBEL as main and sub consultants implement consulting and supervising works.
VietnamEnergy.vn