Inaugurating Vinh Tan 4 Thermal power plant

Inaugurating Vinh Tan 4 Thermal power plant

On morning September 21, 2019, in Vinh Tan power center (Tuy Phong district, Binh Thuan province), Electricity of Vietnam (EVN) held the ceremony for inaugurating Vinh Tan 4 Thermal power plant (TPP). Mr. Truong Hoa Binh - Standing Deputy Prime Minister attended the ceremony and cut the inauguration ribbon.
The Extended Vinh Tan 4 TPP has been successfully synchronized with the NPS

The Extended Vinh Tan 4 TPP has been successfully synchronized with the NPS

At 10:30, on April 22, 2019, in Vinh Tan Power Center, the Extended Vinh Tan 4 Thermal Power Project (TPP) was the first time successfully synchronized with the national power system exceeding the schedule for 71 days in comparison with the plan under the Contract as July 1, 2019.
The unit No2 of Vinh Tan 4 TPP has been successfully synchronized

The unit No2 of Vinh Tan 4 TPP has been successfully synchronized

According to the information from Electricity of Vietnam (EVN), at 10:25 on Oct. 3, 2017, the unit No2 of Vinh Tan 4 Thermal Power Plant (TPP) has been successfully synchronized with the National Power System. This is an important milestone for completing the test to put the unit No2 into commercial operation in August of 2018.
Coal combustion for the first time in Unit N#2 boiler of Vinh Tan 4 TPP

Coal combustion for the first time in Unit N#2 boiler of Vinh Tan 4 TPP

According to the information from GENCO 3, at 12:20 on June 27, 2017, coal burning for the first time at Unit#2 (600MW) of Vinh Tan 4 thermal power plant (TPP) was successfully implemented This is an important milestone as a basis for following testing steps with an aim to commercial operating Unit#2 at the end of 2017.
Doosan Vina begins with the first Power Shipment to Vinh Tan 4 TPP in 2016

Doosan Vina begins with the first Power Shipment to Vinh Tan 4 TPP in 2016

On 17 February 2016, Doosan Vina started the Year of the Monkey on the Lunar Calendar Doosan Vina’s Boiler Shop shipped 354 tons of high tech boiler components to the Vinh Tan 4 thermal power plant in Binh Thuan Province. This is also the first shipment for Doosan Vina of 2016.
Successful Installation of Boiler Main Girder of Vinh Tan 4 Power Plant

Successful Installation of Boiler Main Girder of Vinh Tan 4 Power Plant

After nearly 15 months of construction, on June 17th, 2015, at the Vinh Tan Commune, Tuy Phong District, Binh Thuan Province, the consortium of Doosan Vina contractors held a ceremony to lift and place the "Heavy Girder" for Unit 1 of Vinh Tan 4.