RSS Feeds for Powering May 01, 2024 17:39
Vietnam Energy Forum
Powering Ninh Phuoc 220 kV transformer substation  and connecting power lines

Powering Ninh Phuoc 220 kV transformer substation and connecting power lines

After a period of construction efforts, at 4:30 on June 29, 2020, in Ninh Phuoc 220 kV transformer substation (TS), the Power Project Management Board of the Central Region in cooperation with relevant units organized powering and putting into operation Ninh Phuoc 220 kV transformer substation and connecting power lines.
Powering the shunt reactor at Vung Ang 500 kV transformer substation

Powering the shunt reactor at Vung Ang 500 kV transformer substation

Power Transmission Company No.3 (PTC3) in coordination with related units has put into operation the shunt reactor of 500 kV - 128 MVAr - KH591 at the Vung Ang 500kV transformer substation (TS).
Powering the 110kV Dong Anh – Van Tri second circuit

Powering the 110kV Dong Anh – Van Tri second circuit

Implementing a series of activities of customer grateful Month, on December 20, 2016, Hanoi Power Corporation (EVN HANOI) had powered the 110kV Dong Anh – Van Tri second circuit to ensure electricity supply and strengthen reliability for power grid of Hanoi northern districts.
Powering the transformer AT2 in Son La 500 kV Transformer Substation

Powering the transformer AT2 in Son La 500 kV Transformer Substation

The National Power Transmission Corporation (EVN NPT) has just powered the 500 kV-900 MW Transformer AT2 in Son La 500 kV Transformer Substation under the project “Raising capacity of Son La 500 kV Transformer Substation”. The National Power Transmission Corporation (EVN NPT) has just powered the 500 kV-900 MW Transformer AT2 in Son La 500 kV Transformer Substation under the project “Raising capacity of Son La 500 kV Transformer Substation”
Powering  series capacitor set at Ha Tinh 500kV Transformer Substation

Powering series capacitor set at Ha Tinh 500kV Transformer Substation

On March 31, EVNNPT successfully energized and put into safe operation the 500kV-30,5Ω-2000A series capacitor set at Ha Tinh 500kV Transformer Substation, completed entire the project "Increasing the capacity of series capacitors on Nho Quan – Ha Tinh 500kV transmission line ".