thai binh 2 thermal power plant has been made the cooling pipe system by vietnam

Thai Binh 2 Thermal Power Plant has been made the Cooling Pipe System by Vietnam

Petroleum Pipeline and Tank Construction Joint Stock Company (PVC-PT) has held a starting ceremony for the bidding package "Manufacture and installation of cooling water supplying and draining pipeline system " for Thai Binh 2 Thermal Power Project (TPP).
phuoc thai 1 spp has been put into commercial operation

Phuoc Thai 1 SPP has been put into commercial operation

On August 7, 2020  in Ninh Thuan province, Mr. Nguyen Tai Anh - Deputy General Director of  Electricity of Vietnam (EVN), Chairman of the Investor - level Acceptance Council of EVN and members of the Council have tested  and accepted and put into use the Phuoc Thai 1 solar power plant.
signing the contract for the ash and slag discharging system of thai binh 2 thermal power plant

Signing the contract for the ash and slag discharging system of Thai Binh 2 Thermal Power Plant

PetroVietnam Construction Joint Stock Company (PVC) and the consortium of bidders - PVC-PT / MIE / Viettronics have signed a contract for design, materials and equipment supply, installation and test operation of the ash and slag discharging system of Thai Binh 2 Thermal Power Plant (TPP).
signing contract on the construction of tight coal storages for thai binh 2 thermal power project

Signing contract on the construction of tight coal storages for Thai Binh 2 Thermal Power Project.

On October 6, 2014, in Thai Binh province, PetroVietnam  Construction JSC  (PVC) and PVC Contractors Consortium of Thai Bình JSC Petroleum Investment and Trade Company (PVC TB), Song Da (Da River) JSC Petroleum Investment and Trade Company (PVSD) and  Consulting Company Ltd of National University of Civil Engineering (CCU) signed a contract on "design, estimate, supply and installation of steel structures and construction part implementation of the 3 tight storages” Package for Thai Binh 2  Thermal Power Plant (TPP) with a VND 914 billion value.
ground breaking to build phuoc thai 1 solar power project

Ground breaking to build Phuoc Thai 1 solar power project

On September 26, 2019, in Phuoc Thai commune, Ninh Phuoc district, Ninh Thuan province, the Power Project Management Board 3 (Electricity of Vietnam) held a groundbreaking ceremony for building Phuoc Thai 1 solar power project.
planning for floating storage to receive lng for thai binh lng power center

Planning for floating storage to receive LNG for Thai Binh LNG Power Center

The Ministry of Transport has just issued a document to agree on the policy of planning a floating warehouse to receive 150.000 tons of LNG in the Tra Ly coat for the Thai Binh LNG Power Center with the proposal of the Thai Binh Provincial People's Committee.
pressure test of boiler no 2 of thai binh 2 thermal power plant has been successful implemented

Pressure test of boiler No 2 of Thai Binh 2 Thermal Power Plant has been successful implemented

The Vietnam Lilama Corporation has successfully implemented high pressure test of boiler No2 of Thai Binh 2 Thermal Power Plant under witness and control of the experts from PetroVietnam.
binh thuan province will maximally create the favorable conditions for son my 1 tpp

Binh Thuan province will maximally create the favorable conditions for Son My 1 TPP

Recently, at the meeting with the consortium of contractors (France EDF, Japan Sojitz and Vietnam Pacific company) of Son My 1 thermal power plant (TPP), Standing Vice Chairman of Binh Thuan Provincial People's Committee (PPC) Luong Van Hai affirmed to maximally create the favorable conditions for Son My 1 thermal power project to be deployed and come into operation as soon as possible.