RSS Feeds for Kết quả tìm kiếm từ khóa: Thai Binh 2 | Trang 2 May 15, 2024 21:15
Vietnam Energy Forum
oda loan agreement for thai binh thermal power plant ratified

ODA loan Agreement for Thai Binh Thermal Power Plant ratified

The PM has approved the Official Development Assistance (ODA) loan Agreement between the Vietnamese Government and the Japan International Cooperation Agency (JICA) for Thai Binh Thermal Power Plant and Transmission Lines Construction Project (IV).
powering the thai binh nam dinh 220kv second circuit transmission line

Powering the Thai Binh - Nam Dinh 220kV second circuit transmission line

Vietnam National Power Transmission Corporation (EVN NPT) has just put into operation the Thai Binh- Nam Dinh 220kV second circuit transmission line.
thai binh province committed to ensuring site progress for the 500kvproject with 3 circuit line

Thai Binh province committed to ensuring site progress for the 500kVproject with 3 circuit line

On January 22, 2024, in Thai Binh, The Electricity of Vietnam (EVN), National Power Transmission Corporation (EVNNPT) had a working session with the Thai Binh Provincial People's Committee on power supply and investment in the construction of power projects in Thai Binh province, with the center on the 500 kV circuit 3 line project (Nam Dinh 1 thermal power plant - Pho Noi section). At the meeting, Thai Binh province committed to ensuring the progress of handing over the project's foundation locations (in February) and route corridor (in March 2024) as requested by EVN and EVNNPT.
starting construction of phuoc thai 2 and 3 solar power projects

Starting construction of Phuoc Thai 2 and 3 solar power projects

The starting construction ceremony of Phuoc Thai 2 and Phuoc Thai 3 solar power projects has just taken place in Phuoc Thai commune, Ninh Phuoc district, Ninh Thuan province.
planning for floating storage to receive lng for thai binh lng power center

Planning for floating storage to receive LNG for Thai Binh LNG Power Center

The Ministry of Transport has just issued a document to agree on the policy of planning a floating warehouse to receive 150.000 tons of LNG in the Tra Ly coat for the Thai Binh LNG Power Center with the proposal of the Thai Binh Provincial People's Committee.
unit1 of thai binh 1 thermal power plant has synchronized with the national power system

Unit#1 of Thai Binh 1 Thermal Power Plant has synchronized with the National Power System

At 18.00 on 23 May 2017, Unit#1 of Thai Binh1 Thermal Power Plant (TPP) has successfully connected to the National Power System.