The Extended Vinh Tan 4 TPP has been successfully synchronized with the NPS

The Extended Vinh Tan 4 TPP has been successfully synchronized with the NPS

At 10:30, on April 22, 2019, in Vinh Tan Power Center, the Extended Vinh Tan 4 Thermal Power Project (TPP) was the first time successfully synchronized with the national power system exceeding the schedule for 71 days in comparison with the plan under the Contract as July 1, 2019.
H5 unit of Da Nhim HPP has been  successfully synchronized with the Power System

H5 unit of Da Nhim HPP has been successfully synchronized with the Power System

On December 25, 2018 after 3 year implementation, the Da Nhim – Ham Thuan - Da my Hydropower JSC and relevant constructors carried out successfully synchronizing the extended H5 unit of Da Nhim Hydropower Plant (HPP) with the Power System.