Receiving the first commercial oil flow from the BK-4A platform of Bach Ho field
11:42 | 23/12/2023
- At 3:00 p.m. on December 18, 2023, the Vietnam - Russia Joint Venture Vietsovpetro was pleased to welcome the first commercial oil flow from the BK-4A platform of Bach Ho field (12 days earlier than planned).
Platform BK-4A of Bach Ho field |
BK-4A rig project including:
- Conversion of the BK-4A rig into a wellhead rig.
- Conversion of BK-4 rig.
- Transferring 26" underground pipeline NCS2-BK4A (launched on August 18, 2023), approved for acceptance and completion and put into use (November 24, 2023).
The acceptance council of Vietsovpetro assessed that the project was completed to ensure absolute quality and safety.
Receiving the first commercial oil flow from the BK-4A platform of Bach Ho field (12 days earlier than planned), along with the combination of RC-8 and BK-22 projects has contributed to increasing exploitation output oil in 2023 and the following years of Vietsovpetro./.