Thanh Hoa Approves Investment Policy and Investor for Trung Son Hydropower Plant Expansion Project

 - The Thanh Hoa Provincial People's Committee has issued Decision No. 3816/QD-UBND dated November 11, 2026, approving the investment policy and the investor for the Trung Son Hydropower Plant Expansion Project in Trung Son Commune, Thanh Hoa Province. The approved investor is Trung Son Hydropower One-Member Limited Liability Company, which is wholly owned by Power Generation Corporation 2 (EVNGENCO2).

Key project information

  • Expansion capacity: 130 MW (2 × 65 MW).

  • Investor: Trung Son Hydropower One-Member Limited Liability Company.

  • Total investment capital: Approximately VND 2,912.74 billion, comprising 18.67% equity (VND 543.68 billion) and 81.33% commercial loans (VND 2,369.06 billion).

  • Land area and project term: Approximately 17.546 hectares, including 8.07 hectares for permanent use and 9.476 hectares for temporary use. The project has an operating term of 40 years from the effective date of the investment policy approval. It will share the reservoir and dam infrastructure of the existing Trung Son Hydropower Plant.

  • Implementation schedule: Complete the procedures for land allocation or lease within 12 months from the effective date of the approval decision, and complete construction and commence power generation no later than 42 months from the date the State hands over the project land.

The expansion project will be located on the left bank of the existing dam. Its main components will include a headrace channel, water intake structure, pressure tunnel, powerhouse and tailrace channel, together with auxiliary facilities.

Electricity generated by the expanded plant will be connected to the national power system via a 220 kV transmission line linking to an additional feeder bay at the 220 kV switchyard of the existing Trung Son Hydropower Plant. The project will share the existing reservoir, dam, spillway and flood regulation facilities.

Under the decision, the investor must complete the required documentation and procedures to obtain land allocation or lease rights for the land area for which land-use rights have not yet been secured within 12 months from the effective date of the approval decision. Failure to meet this deadline will render the approval decision legally invalid.

The project must be completed and commence power generation no later than 42 months from the date the State hands over the land for project implementation.

Approval of the investment policy does not, however, mean that construction can begin immediately. The investor must first complete all relevant procedures relating to investment, construction, land use, forestry, environmental protection, water resources, disaster prevention and control, and dam and reservoir safety.

In addition, the feasibility study report must assess the potential impacts of the expansion project on the existing hydropower plant, dam and reservoir safety, flow regimes, downstream areas, the former Co Me resettlement area and residential communities along the Ma River. Where there is a risk of landslides, the investor must propose appropriate mitigation measures and implement the necessary protective works to address such risks./.