unit1 of thai binh 1 thermal power plant has synchronized with the national power system

Unit#1 of Thai Binh 1 Thermal Power Plant has synchronized with the National Power System

At 18.00 on 23 May 2017, Unit#1 of Thai Binh1 Thermal Power Plant (TPP) has successfully connected to the National Power System.
first igniting for unit 1 of thai binh 2 thermal power plant

First igniting for unit 1 of Thai Binh 2 Thermal Power Plant

On the morning of 23 February 2022, Deputy Prime Minister (DPM) Le Van Thanh came to check the progress of the Thai Binh 2 Thermal Power Project (TPP). DPM welcomed the important milestone of the Thai Binh 2 TPP as the first igniting and considered that this is an important milestone for the project to finish in 2022.
unit 1 of thai binh 2 tpp has synchronized with the national power system

Unit 1 of Thai Binh 2 TPP has synchronized with the National Power System

On the May 13 afternoon, at Thai Binh 2 Thermal Power Plant (TPP), the Vietnam Oil and Gas Group (PVN) held a ceremony for successful synchronizing unit 1 of Thai Binh 2 TPP with the National Power System.
successful pressure tests for boiler 1 and low pressure package of boiler 2 in thai binh 2 thermal power plant

Successful pressure tests for boiler 1 and low pressure package of boiler 2 in Thai Binh 2 thermal power plant

At 11:30 a.m on August 13th 2016, in the construction site of Thai Binh 2 thermal power plant, LILAMA Corporation has conducted successfully pressure test (of Low Pressure Package) for Boiler 2 and finished pressure test (of High Pressure Package) for Boiler 1.
the first commercial gas flow from thai binh field

The first commercial gas flow from Thai Binh field

PetroVietnam Exploration and Production Corporation (PVEP) informed: the Project on Development the Thai Binh Gas Field, at 102-106 Lots of Song Hong Basin offshore Gulf of Tonkin under the PCOSB Operator has given the first commercial gas flow of a 5 million cubic feet per day output (1 cubic foot is equivalent to 0.028 cubic meter) from TB-1P Well.
launching the thai binh exploiting rig base

Launching the Thai Binh exploiting rig base

On the ground of PVC-MS harbor, PetroVietnam Equipment Assembly and Metal Structrure Joint Stock Company (PVC -MS, stocks code: PXS) has successfully launched the Thai Binh exploiting rig base.
thai binh sos childrens village has been inaugurated

Thai Binh SOS Children's Village has been inaugurated

On January 21, 2015, in Thai Binh, the Ministry of Labour - Invalids and Social Affairs (MOLISA) in collaboration with Thai Binh Provincial People Committee (PPC) and PV Drilling (PetroVietnam) organized  the  Inauguration Ceremony of Thai Binh SOS Children's Village.
pm attends inaugural ceremony of thai binh thermal plant

PM attends inaugural ceremony of Thai Binh Thermal Plant

Prime Minister Nguyen Xuan Phuc on February 14 cut the ribbon to inaugurate the Thai Binh Thermal Power Plant in the northern province’s Thai Thuy district.   
vinacomin has started up 440 mw tpp in thai binh province

Vinacomin has started up 440 MW TPP in Thai Binh province

With agreement of Thai Binh provincial people’s committee, Vinacomin directed Vinacomin Power Corporation to develop the 440 MW coal-fired thermal power plant in Thai Binh thermal power center.
launching thai binh lng gas power joint stock company

Launching Thai Binh LNG Gas Power Joint Stock Company

The investor consortium including Vietnam Truong Thanh Group Joint Stock Company (TTVN Group) and Japan Tokyo Gas and Kyunden Company had just held the launching ceremony of Thai Binh LNG Gas Power Joint Stock Company (in Thai Do commune, Thai Thuy district, Thai Binh Province). Previously.
signing contracts for perfecting thai binh 2 thermal power project

Signing contracts for perfecting Thai Binh 2 Thermal Power Project

In Hanoi, PetroVietnam Construction Joint Stock Corporation (PVC) the EPC contractor of Thai Binh 2 Thermal Power Project (TPP) held the ceremony for signing five important contracts under the completion stage Thai Binh 2 TPP.
oda loan agreement for thai binh thermal power plant ratified

ODA loan Agreement for Thai Binh Thermal Power Plant ratified

The PM has approved the Official Development Assistance (ODA) loan Agreement between the Vietnamese Government and the Japan International Cooperation Agency (JICA) for Thai Binh Thermal Power Plant and Transmission Lines Construction Project (IV).
powering the thai binh nam dinh 220kv second circuit transmission line

Powering the Thai Binh - Nam Dinh 220kV second circuit transmission line

Vietnam National Power Transmission Corporation (EVN NPT) has just put into operation the Thai Binh- Nam Dinh 220kV second circuit transmission line.
thai binh province committed to ensuring site progress for the 500kvproject with 3 circuit line

Thai Binh province committed to ensuring site progress for the 500kVproject with 3 circuit line

On January 22, 2024, in Thai Binh, The Electricity of Vietnam (EVN), National Power Transmission Corporation (EVNNPT) had a working session with the Thai Binh Provincial People's Committee on power supply and investment in the construction of power projects in Thai Binh province, with the center on the 500 kV circuit 3 line project (Nam Dinh 1 thermal power plant - Pho Noi section). At the meeting, Thai Binh province committed to ensuring the progress of handing over the project's foundation locations (in February) and route corridor (in March 2024) as requested by EVN and EVNNPT.
successful pressure test for boiler no1 of thai binh 2 thermal power plant

Successful pressure test for boiler No1 of Thai Binh 2 Thermal Power Plant

Vietnam Lilama Corporation constructor has successfully implemented a pressure test for boiler No1 of Thai Binh 2 Thermal Power Plant. The test results satisfy planed technical parameters.  