First igniting for unit 1 of Thai Binh 2 Thermal Power Plant
15:40 | 24/02/2022
The Deputy Prime Minister welcomed the successful milestone of the project's important progress (Photo: VGP/Duc Tuan). |
According to the Vietnam National Oil and Gas Group (PVN) - the project investor, up to now, the project reaches progress of 88.75% including the design work of nearly 100%, material and equipment procurement of nearly 96%, construction and installation of nearly 88% and test running of nearly 26%.
Exchanging views with PVN officials, contractors, the workers of the construction units, at the construction site, DPM Le Van Thanh highly appreciated and praised the investor, the project management board, and the EPC general contractor for the high responsibility, strength, methodical and scientific implementations in the organization, financial, personnel activities, administration and contracts.
Up to now "We have successfully organized the first ignition milestone for unit 1 by oil in the time schedule as planned”, said DPM.
The DPM requested to mobilize the means to ensure the planned progress milestones, in which to strive for connecting with the power system by oil on April 30, 2022.
The successful igniting for unit 1 of Thai Binh 2 TPP (Photo: VGP/Duc Tuan). |
DPM is also required for ensuring absolute safety in the project construction, installation, test running and operation; improving the adequate care on health, material and spiritual life of employees; coordinating with Thai Binh local authorities to well ensure security inside and outside of the power plant.
The Deputy Prime Minister emphasized environmental protection and “greening” the construction site.
After inspecting, DPM Le Van Thanh had a meeting with the leaders of PVN, contractors and construction units about the project.
After inspecting, DPM Le Van Thanh had a meeting with the leaders of PVN, contractors and construction units about the project.