Pressure test of boiler No 2 of Thai Binh 2 Thermal Power Plant has been successful implemented
08:15 | 21/12/2016
The Vietnam Lilama Corporation has successfully implemented high pressure test of boiler No2 of Thai Binh 2 Thermal Power Plant under witness and control of the experts from PetroVietnam.
First igniting for unit 1 of Thai Binh 2 Thermal Power Plant
15:40 | 24/02/2022
On the morning of 23 February 2022, Deputy Prime Minister (DPM) Le Van Thanh came to check the progress of the Thai Binh 2 Thermal Power Project (TPP). DPM welcomed the important milestone of the Thai Binh 2 TPP as the first igniting and considered that this is an important milestone for the project to finish in 2022.
Successful pressure test for boiler No1 of Thai Binh 2 Thermal Power Plant
08:53 | 27/07/2016
Vietnam Lilama Corporation constructor has successfully implemented a pressure test for boiler No1 of Thai Binh 2 Thermal Power Plant. The test results satisfy planed technical parameters.
Thai Binh 2 Thermal Power Plant has been made the Cooling Pipe System by Vietnam
09:16 | 27/05/2015
Petroleum Pipeline and Tank Construction Joint Stock Company (PVC-PT) has held a starting ceremony for the bidding package "Manufacture and installation of cooling water supplying and draining pipeline system " for Thai Binh 2 Thermal Power Project (TPP).
Signing the contract for the ash and slag discharging system of Thai Binh 2 Thermal Power Plant
10:46 | 05/06/2015
PetroVietnam Construction Joint Stock Company (PVC) and the consortium of bidders - PVC-PT / MIE / Viettronics have signed a contract for design, materials and equipment supply, installation and test operation of the ash and slag discharging system of Thai Binh 2 Thermal Power Plant (TPP).
Successful pressure tests for boiler 1 and low pressure package of boiler 2 in Thai Binh 2 thermal power plant
17:23 | 16/08/2016
At 11:30 a.m on August 13th 2016, in the construction site of Thai Binh 2 thermal power plant, LILAMA Corporation has conducted successfully pressure test (of Low Pressure Package) for Boiler 2 and finished pressure test (of High Pressure Package) for Boiler 1.
ODA loan Agreement for Thai Binh Thermal Power Plant ratified
18:06 | 31/05/2016
The PM has approved the Official Development Assistance (ODA) loan Agreement between the Vietnamese Government and the Japan International Cooperation Agency (JICA) for Thai Binh Thermal Power Plant and Transmission Lines Construction Project (IV).
Unit#1 of Thai Binh 1 Thermal Power Plant has synchronized with the National Power System
09:28 | 25/05/2017
At 18.00 on 23 May 2017, Unit#1 of Thai Binh1 Thermal Power Plant (TPP) has successfully connected to the National Power System.
Signing contracts for perfecting Thai Binh 2 Thermal Power Project
14:09 | 10/09/2018
In Hanoi, PetroVietnam Construction Joint Stock Corporation (PVC) the EPC contractor of Thai Binh 2 Thermal Power Project (TPP) held the ceremony for signing five important contracts under the completion stage Thai Binh 2 TPP.
Signing contract on the construction of tight coal storages for Thai Binh 2 Thermal Power Project.
16:06 | 09/10/2014
On October 6, 2014, in Thai Binh province, PetroVietnam Construction JSC (PVC) and PVC Contractors Consortium of Thai Bình JSC Petroleum Investment and Trade Company (PVC TB), Song Da (Da River) JSC Petroleum Investment and Trade Company (PVSD) and Consulting Company Ltd of National University of Civil Engineering (CCU) signed a contract on "design, estimate, supply and installation of steel structures and construction part implementation of the 3 tight storages” Package for Thai Binh 2 Thermal Power Plant (TPP) with a VND 914 billion value.
PM attends inaugural ceremony of Thai Binh Thermal Plant
14:30 | 16/02/2019
Prime Minister Nguyen Xuan Phuc on February 14 cut the ribbon to inaugurate the Thai Binh Thermal Power Plant in the northern province’s Thai Thuy district.
Inaugurating the Unit 1 of Nghi Son BOT Thermal Power Plant 2
16:36 | 15/02/2022
On the morning of February 10, 2022, Nghi Son 2 Electric Co., Ltd. in coordination with the investor, Korea Electricity Corporation (Kepco) and Marubeni Group, Tohoku Company (Japan) held the inauguration ceremony of unit No. 1 of Nghi Son BOT Thermal Power Plant 2.
Doosan announces the kickoff of the Nghi Son 2 Thermal Power Plant project in Vietnam
08:44 | 25/07/2018
Doosan Heavy Industries and Construction (DHIC) today announced that it had received the initial payment for the $2.79 billion 1,330 MW Nghi Son 2 (NS-2) Power Plant which formally signals commencement of the project that was awarded in late 2014.
Nhon Trach 2 thermal power plant produces 35 billion kWh in 7 years
15:10 | 13/12/2018
The Nhon Trach 2 thermal power plant in the southern province of Dong Nai has generated 35 billion kWh for the national grid over just seven years of operation, announced the PetroVietnam Power Nhon Trach 2 company on November 20th.
Unit No. 2 of Vung Ang 1 Thermal Power Plant has been officially put into commercial operation
23:15 | 14/05/2015
On May 12, Limama EPC general contractor handed over the Unit No. 2 of Vung Ang 1 Thermal Power Plant (TPP) to the Petroietnam (PVN) investor for commercial operation.