Starting manufacturing ST PIP compressor for the White Lion mine
08:36 | 03/02/2015
This project belongs to the plan of developing White Mine of Cuu Long JOC Investor with PTSC M&C contractor for material procurement, manufacture and construction.
For the first stage of developing White Lion Mine Project, PTSC M&C will carry out general EPCI for the items as ST PIP compressor with a 2500MT four leg support, an about 4100MT higher layer block, a 1600MT pile system, a 300MT water splitting pipe system; a ST LQ housing rig with an about 950MT support and an about 1250MT higher layer block; two conducting bridges from ST PIP compressor to ST LQ housing rig and from ST PIP compressor to STT LTPTP rig (already available) with a 100m length and a 120MT weight each.
The Project has started since the end of October, 2014, and expected to be complete by September 2016, the anticipating date for clearing the gas first flow according to the investor’ requirement.