Vietnam Energy Online - Search results for keyword "Thai Binh 2". Hope you find the content you want on https://vietnamenergy.vn/
Pressure test of boiler No 2 of Thai Binh 2 Thermal Power Plant has been successful implemented
08:15 | 21/12/2016
The Vietnam Lilama Corporation has successfully implemented high pressure test of boiler No2 of Thai Binh 2 Thermal Power Plant under witness and control of the experts from PetroVietnam.
First igniting for unit 1 of Thai Binh 2 Thermal Power Plant
15:40 | 24/02/2022
On the morning of 23 February 2022, Deputy Prime Minister (DPM) Le Van Thanh came to check the progress of the Thai Binh 2 Thermal Power Project (TPP). DPM welcomed the important milestone of the Thai Binh 2 TPP as the first igniting and considered that this is an important milestone for the project to finish in 2022.
Signing contracts for perfecting Thai Binh 2 Thermal Power Project
14:09 | 10/09/2018
In Hanoi, PetroVietnam Construction Joint Stock Corporation (PVC) the EPC contractor of Thai Binh 2 Thermal Power Project (TPP) held the ceremony for signing five important contracts under the completion stage Thai Binh 2 TPP.
Successful pressure tests for boiler 1 and low pressure package of boiler 2 in Thai Binh 2 thermal power plant
17:23 | 16/08/2016
At 11:30 a.m on August 13th 2016, in the construction site of Thai Binh 2 thermal power plant, LILAMA Corporation has conducted successfully pressure test (of Low Pressure Package) for Boiler 2 and finished pressure test (of High Pressure Package) for Boiler 1.
Unit 1 of Thai Binh 2 TPP has synchronized with the National Power System
08:58 | 17/05/2022
On the May 13 afternoon, at Thai Binh 2 Thermal Power Plant (TPP), the Vietnam Oil and Gas Group (PVN) held a ceremony for successful synchronizing unit 1 of Thai Binh 2 TPP with the National Power System.
Successful pressure test for boiler No1 of Thai Binh 2 Thermal Power Plant
08:53 | 27/07/2016
Vietnam Lilama Corporation constructor has successfully implemented a pressure test for boiler No1 of Thai Binh 2 Thermal Power Plant. The test results satisfy planed technical parameters.
Thai Binh 2 Thermal Power Plant has been made the Cooling Pipe System by Vietnam
09:16 | 27/05/2015
Petroleum Pipeline and Tank Construction Joint Stock Company (PVC-PT) has held a starting ceremony for the bidding package "Manufacture and installation of cooling water supplying and draining pipeline system " for Thai Binh 2 Thermal Power Project (TPP).
Signing the contract for the ash and slag discharging system of Thai Binh 2 Thermal Power Plant
10:46 | 05/06/2015
PetroVietnam Construction Joint Stock Company (PVC) and the consortium of bidders - PVC-PT / MIE / Viettronics have signed a contract for design, materials and equipment supply, installation and test operation of the ash and slag discharging system of Thai Binh 2 Thermal Power Plant (TPP).
Signing contract on the construction of tight coal storages for Thai Binh 2 Thermal Power Project.
16:06 | 09/10/2014
On October 6, 2014, in Thai Binh province, PetroVietnam Construction JSC (PVC) and PVC Contractors Consortium of Thai Bình JSC Petroleum Investment and Trade Company (PVC TB), Song Da (Da River) JSC Petroleum Investment and Trade Company (PVSD) and Consulting Company Ltd of National University of Civil Engineering (CCU) signed a contract on "design, estimate, supply and installation of steel structures and construction part implementation of the 3 tight storages” Package for Thai Binh 2 Thermal Power Plant (TPP) with a VND 914 billion value.
The first commercial gas flow from Thai Binh field
08:10 | 11/08/2015
PetroVietnam Exploration and Production Corporation (PVEP) informed: the Project on Development the Thai Binh Gas Field, at 102-106 Lots of Song Hong Basin offshore Gulf of Tonkin under the PCOSB Operator has given the first commercial gas flow of a 5 million cubic feet per day output (1 cubic foot is equivalent to 0.028 cubic meter) from TB-1P Well.
Launching the Thai Binh exploiting rig base
09:29 | 27/03/2015
On the ground of PVC-MS harbor, PetroVietnam Equipment Assembly and Metal Structrure Joint Stock Company (PVC -MS, stocks code: PXS) has successfully launched the Thai Binh exploiting rig base.
Thai Binh SOS Children's Village has been inaugurated
10:15 | 26/01/2015
On January 21, 2015, in Thai Binh, the Ministry of Labour - Invalids and Social Affairs (MOLISA) in collaboration with Thai Binh Provincial People Committee (PPC) and PV Drilling (PetroVietnam) organized the Inauguration Ceremony of Thai Binh SOS Children's Village.
PM attends inaugural ceremony of Thai Binh Thermal Plant
14:30 | 16/02/2019
Prime Minister Nguyen Xuan Phuc on February 14 cut the ribbon to inaugurate the Thai Binh Thermal Power Plant in the northern province’s Thai Thuy district.
Vinacomin has started up 440 MW TPP in Thai Binh province
08:30 | 25/07/2018
With agreement of Thai Binh provincial people’s committee, Vinacomin directed Vinacomin Power Corporation to develop the 440 MW coal-fired thermal power plant in Thai Binh thermal power center.
Launching Thai Binh LNG Gas Power Joint Stock Company
13:36 | 30/01/2024
The investor consortium including Vietnam Truong Thanh Group Joint Stock Company (TTVN Group) and Japan Tokyo Gas and Kyunden Company had just held the launching ceremony of Thai Binh LNG Gas Power Joint Stock Company (in Thai Do commune, Thai Thuy district, Thai Binh Province). Previously.