Unit 1 of Thai Binh 2 TPP has synchronized with the National Power System
08:58 | 17/05/2022
On the May 13 afternoon, at Thai Binh 2 Thermal Power Plant (TPP), the Vietnam Oil and Gas Group (PVN) held a ceremony for successful synchronizing unit 1 of Thai Binh 2 TPP with the National Power System.
Vinacomin has started up 440 MW TPP in Thai Binh province
08:30 | 25/07/2018
With agreement of Thai Binh provincial people’s committee, Vinacomin directed Vinacomin Power Corporation to develop the 440 MW coal-fired thermal power plant in Thai Binh thermal power center.
Pressure test of boiler No 2 of Thai Binh 2 Thermal Power Plant has been successful implemented
08:15 | 21/12/2016
The Vietnam Lilama Corporation has successfully implemented high pressure test of boiler No2 of Thai Binh 2 Thermal Power Plant under witness and control of the experts from PetroVietnam.
First igniting for unit 1 of Thai Binh 2 Thermal Power Plant
15:40 | 24/02/2022
On the morning of 23 February 2022, Deputy Prime Minister (DPM) Le Van Thanh came to check the progress of the Thai Binh 2 Thermal Power Project (TPP). DPM welcomed the important milestone of the Thai Binh 2 TPP as the first igniting and considered that this is an important milestone for the project to finish in 2022.
Signing contracts for perfecting Thai Binh 2 Thermal Power Project
14:09 | 10/09/2018
In Hanoi, PetroVietnam Construction Joint Stock Corporation (PVC) the EPC contractor of Thai Binh 2 Thermal Power Project (TPP) held the ceremony for signing five important contracts under the completion stage Thai Binh 2 TPP.
Successful pressure tests for boiler 1 and low pressure package of boiler 2 in Thai Binh 2 thermal power plant
17:23 | 16/08/2016
At 11:30 a.m on August 13th 2016, in the construction site of Thai Binh 2 thermal power plant, LILAMA Corporation has conducted successfully pressure test (of Low Pressure Package) for Boiler 2 and finished pressure test (of High Pressure Package) for Boiler 1.
Successful pressure test for boiler No1 of Thai Binh 2 Thermal Power Plant
08:53 | 27/07/2016
Vietnam Lilama Corporation constructor has successfully implemented a pressure test for boiler No1 of Thai Binh 2 Thermal Power Plant. The test results satisfy planed technical parameters.
Thai Binh 2 Thermal Power Plant has been made the Cooling Pipe System by Vietnam
09:16 | 27/05/2015
Petroleum Pipeline and Tank Construction Joint Stock Company (PVC-PT) has held a starting ceremony for the bidding package "Manufacture and installation of cooling water supplying and draining pipeline system " for Thai Binh 2 Thermal Power Project (TPP).
Binh Thuan province will maximally create the favorable conditions for Son My 1 TPP
10:26 | 31/08/2018
Recently, at the meeting with the consortium of contractors (France EDF, Japan Sojitz and Vietnam Pacific company) of Son My 1 thermal power plant (TPP), Standing Vice Chairman of Binh Thuan Provincial People's Committee (PPC) Luong Van Hai affirmed to maximally create the favorable conditions for Son My 1 thermal power project to be deployed and come into operation as soon as possible.
Signing the contract for the ash and slag discharging system of Thai Binh 2 Thermal Power Plant
10:46 | 05/06/2015
PetroVietnam Construction Joint Stock Company (PVC) and the consortium of bidders - PVC-PT / MIE / Viettronics have signed a contract for design, materials and equipment supply, installation and test operation of the ash and slag discharging system of Thai Binh 2 Thermal Power Plant (TPP).
Signing contract on the construction of tight coal storages for Thai Binh 2 Thermal Power Project.
16:06 | 09/10/2014
On October 6, 2014, in Thai Binh province, PetroVietnam Construction JSC (PVC) and PVC Contractors Consortium of Thai Bình JSC Petroleum Investment and Trade Company (PVC TB), Song Da (Da River) JSC Petroleum Investment and Trade Company (PVSD) and Consulting Company Ltd of National University of Civil Engineering (CCU) signed a contract on "design, estimate, supply and installation of steel structures and construction part implementation of the 3 tight storages” Package for Thai Binh 2 Thermal Power Plant (TPP) with a VND 914 billion value.
Unit 1 of Nghi Son TPP 2 has been synchronized into the national power system
08:59 | 23/07/2021
At Nghi Son 2 Thermal Power Plant project (Hai Ha commune, Tinh Gia district, Thanh Hoa province), the general contractor and joint venture of contractors have successfully synchronized unit 1 into the national power sýtem. This event marks the efforts of the investor, general contractor and construction contractors to overcome difficulties in the complicated situation of the Covid-19 pandemic.
Unit 2 of Duyen Hai 3 TPP has been officially put into commercial operation
10:48 | 20/04/2017
Duyen Hai Thermal Power Company has officially received Unit 2 of Duyen Hai 3 Thermal Power Plant (TPP) from the Thermal Power Project 3 Management Board, Consultants Contractors.
Coal combustion for the first time in Unit N#2 boiler of Vinh Tan 4 TPP
08:40 | 29/06/2017
According to the information from GENCO 3, at 12:20 on June 27, 2017, coal burning for the first time at Unit#2 (600MW) of Vinh Tan 4 thermal power plant (TPP) was successfully implemented This is an important milestone as a basis for following testing steps with an aim to commercial operating Unit#2 at the end of 2017.
Powering the 500 kV line connecting Nghi Son 2 BOT TPP with the National Power System
08:55 | 29/07/2021
At 3:36 p.m. on July 27, 2021, the Central Power Projects Management Board (CPMB) in coordination with relevant units powering the 500 kV line connecting Nghi Son 2 BOT Thermal Power Plant (TPP) with the National Power System (NPS). The project invested by the National Power Transmission Corporation (EVNNPT), and managed by CPMB on behalf of EVNNPT was started for construction on April 09, 2018.