unit 1 of thai binh 2 tpp has synchronized with the national power system

Unit 1 of Thai Binh 2 TPP has synchronized with the National Power System

On the May 13 afternoon, at Thai Binh 2 Thermal Power Plant (TPP), the Vietnam Oil and Gas Group (PVN) held a ceremony for successful synchronizing unit 1 of Thai Binh 2 TPP with the National Power System.
vinacomin has started up 440 mw tpp in thai binh province

Vinacomin has started up 440 MW TPP in Thai Binh province

With agreement of Thai Binh provincial people’s committee, Vinacomin directed Vinacomin Power Corporation to develop the 440 MW coal-fired thermal power plant in Thai Binh thermal power center.
pressure test of boiler no 2 of thai binh 2 thermal power plant has been successful implemented

Pressure test of boiler No 2 of Thai Binh 2 Thermal Power Plant has been successful implemented

The Vietnam Lilama Corporation has successfully implemented high pressure test of boiler No2 of Thai Binh 2 Thermal Power Plant under witness and control of the experts from PetroVietnam.
first igniting for unit 1 of thai binh 2 thermal power plant

First igniting for unit 1 of Thai Binh 2 Thermal Power Plant

On the morning of 23 February 2022, Deputy Prime Minister (DPM) Le Van Thanh came to check the progress of the Thai Binh 2 Thermal Power Project (TPP). DPM welcomed the important milestone of the Thai Binh 2 TPP as the first igniting and considered that this is an important milestone for the project to finish in 2022.
signing contracts for perfecting thai binh 2 thermal power project

Signing contracts for perfecting Thai Binh 2 Thermal Power Project

In Hanoi, PetroVietnam Construction Joint Stock Corporation (PVC) the EPC contractor of Thai Binh 2 Thermal Power Project (TPP) held the ceremony for signing five important contracts under the completion stage Thai Binh 2 TPP.
successful pressure tests for boiler 1 and low pressure package of boiler 2 in thai binh 2 thermal power plant

Successful pressure tests for boiler 1 and low pressure package of boiler 2 in Thai Binh 2 thermal power plant

At 11:30 a.m on August 13th 2016, in the construction site of Thai Binh 2 thermal power plant, LILAMA Corporation has conducted successfully pressure test (of Low Pressure Package) for Boiler 2 and finished pressure test (of High Pressure Package) for Boiler 1.
successful pressure test for boiler no1 of thai binh 2 thermal power plant

Successful pressure test for boiler No1 of Thai Binh 2 Thermal Power Plant

Vietnam Lilama Corporation constructor has successfully implemented a pressure test for boiler No1 of Thai Binh 2 Thermal Power Plant. The test results satisfy planed technical parameters.  
thai binh 2 thermal power plant has been made the cooling pipe system by vietnam

Thai Binh 2 Thermal Power Plant has been made the Cooling Pipe System by Vietnam

Petroleum Pipeline and Tank Construction Joint Stock Company (PVC-PT) has held a starting ceremony for the bidding package "Manufacture and installation of cooling water supplying and draining pipeline system " for Thai Binh 2 Thermal Power Project (TPP).
binh thuan province will maximally create the favorable conditions for son my 1 tpp

Binh Thuan province will maximally create the favorable conditions for Son My 1 TPP

Recently, at the meeting with the consortium of contractors (France EDF, Japan Sojitz and Vietnam Pacific company) of Son My 1 thermal power plant (TPP), Standing Vice Chairman of Binh Thuan Provincial People's Committee (PPC) Luong Van Hai affirmed to maximally create the favorable conditions for Son My 1 thermal power project to be deployed and come into operation as soon as possible.
signing the contract for the ash and slag discharging system of thai binh 2 thermal power plant

Signing the contract for the ash and slag discharging system of Thai Binh 2 Thermal Power Plant

PetroVietnam Construction Joint Stock Company (PVC) and the consortium of bidders - PVC-PT / MIE / Viettronics have signed a contract for design, materials and equipment supply, installation and test operation of the ash and slag discharging system of Thai Binh 2 Thermal Power Plant (TPP).
signing contract on the construction of tight coal storages for thai binh 2 thermal power project

Signing contract on the construction of tight coal storages for Thai Binh 2 Thermal Power Project.

On October 6, 2014, in Thai Binh province, PetroVietnam  Construction JSC  (PVC) and PVC Contractors Consortium of Thai Bình JSC Petroleum Investment and Trade Company (PVC TB), Song Da (Da River) JSC Petroleum Investment and Trade Company (PVSD) and  Consulting Company Ltd of National University of Civil Engineering (CCU) signed a contract on "design, estimate, supply and installation of steel structures and construction part implementation of the 3 tight storages” Package for Thai Binh 2  Thermal Power Plant (TPP) with a VND 914 billion value.
unit 1 of nghi son tpp 2 has been synchronized into the national power system

Unit 1 of Nghi Son TPP 2 has been synchronized into the national power system

At Nghi Son 2 Thermal Power Plant project (Hai Ha commune, Tinh Gia district, Thanh Hoa province), the general contractor and joint venture of contractors have successfully synchronized unit 1 into the national power sýtem. This event marks the efforts of the investor, general contractor and construction contractors to overcome difficulties in the complicated situation of the Covid-19 pandemic.
unit 2 of duyen hai 3 tpp has been officially put into commercial operation

Unit 2 of Duyen Hai 3 TPP has been officially put into commercial operation

Duyen Hai Thermal Power Company has officially received Unit 2 of Duyen Hai 3 Thermal Power Plant (TPP) from the Thermal Power Project 3 Management Board, Consultants Contractors.
coal combustion for the first time in unit n2 boiler of vinh tan 4 tpp

Coal combustion for the first time in Unit N#2 boiler of Vinh Tan 4 TPP

According to the information from GENCO 3, at 12:20 on June 27, 2017, coal burning for the first time at Unit#2 (600MW) of Vinh Tan 4 thermal power plant (TPP) was successfully implemented This is an important milestone as a basis for following testing steps with an aim to commercial operating Unit#2 at the end of 2017.
powering the 500 kv line connecting nghi son 2 bot tpp with the national power system

Powering the 500 kV line connecting Nghi Son 2 BOT TPP with the National Power System

At 3:36 p.m. on July 27, 2021, the Central Power Projects Management Board (CPMB) in coordination with relevant units powering the 500 kV line connecting Nghi Son 2 BOT Thermal Power Plant (TPP) with the National Power System (NPS). The project invested by the National Power Transmission Corporation (EVNNPT), and managed by CPMB on behalf of EVNNPT was started for construction on April 09, 2018.