RSS Feeds for Kết quả tìm kiếm từ khóa: Song Hau 2 TPP | Trang 1 May 04, 2024 01:23
Vietnam Energy Forum
commencement of installing steel structures for boiler 1 of song hau 1 tpp

Commencement of installing steel structures for Boiler 1 of Song Hau 1 TPP

In the morning of July 31st in Chau Thanh, Hau Giang, Lilama Corporation in coordination with  Vietnam Oil and Gas Group (Petrovietnam) and other contractors conducted the commencement ceremony of installing steel structures for Boiler 1 of Song Hau 1 thermal power plant.
the first fire for the boiler of unit 2 of song hau 1 thermal power project

The first fire for the boiler of Unit 2 of Song Hau 1 thermal power project

On November 5, 2020, Vietnam National Oil and Gas Group (PVN), Song Hau 1 Petroleum Power Project Management Board (Investor), and the General Contractor - Vietnam Machinery Erection Corporation (Lilama) successfully set on the first fire boiler of unit 2 of Song Hau 1 thermal power project (TPP).  This event marks a milestone in success with a planned progress of the project.
toyo ink malaysia is looking for the partners for developing the song hau 2 bot thermal power project

Toyo Ink (Malaysia) is looking for the partners for developing the Song Hau 2 BOT Thermal Power Project

Toyo Ink Group Berhad is promoting a plan to find the partners for capital contributing the investment capital to the US$ 3.5 billion Song Hau 2 BOT Thermal Power Project (TPP), Hau Giang province, Southern Vietnam that has been assigned to the Group for studying development.
unit 1 of thai binh 2 tpp has synchronized with the national power system

Unit 1 of Thai Binh 2 TPP has synchronized with the National Power System

On the May 13 afternoon, at Thai Binh 2 Thermal Power Plant (TPP), the Vietnam Oil and Gas Group (PVN) held a ceremony for successful synchronizing unit 1 of Thai Binh 2 TPP with the National Power System.
unit 1 of nghi son tpp 2 has been synchronized into the national power system

Unit 1 of Nghi Son TPP 2 has been synchronized into the national power system

At Nghi Son 2 Thermal Power Plant project (Hai Ha commune, Tinh Gia district, Thanh Hoa province), the general contractor and joint venture of contractors have successfully synchronized unit 1 into the national power sýtem. This event marks the efforts of the investor, general contractor and construction contractors to overcome difficulties in the complicated situation of the Covid-19 pandemic.
unit 2 of duyen hai 3 tpp has been officially put into commercial operation

Unit 2 of Duyen Hai 3 TPP has been officially put into commercial operation

Duyen Hai Thermal Power Company has officially received Unit 2 of Duyen Hai 3 Thermal Power Plant (TPP) from the Thermal Power Project 3 Management Board, Consultants Contractors.
coal combustion for the first time in unit n2 boiler of vinh tan 4 tpp

Coal combustion for the first time in Unit N#2 boiler of Vinh Tan 4 TPP

According to the information from GENCO 3, at 12:20 on June 27, 2017, coal burning for the first time at Unit#2 (600MW) of Vinh Tan 4 thermal power plant (TPP) was successfully implemented This is an important milestone as a basis for following testing steps with an aim to commercial operating Unit#2 at the end of 2017.
powering the 500 kv line connecting nghi son 2 bot tpp with the national power system

Powering the 500 kV line connecting Nghi Son 2 BOT TPP with the National Power System

At 3:36 p.m. on July 27, 2021, the Central Power Projects Management Board (CPMB) in coordination with relevant units powering the 500 kV line connecting Nghi Son 2 BOT Thermal Power Plant (TPP) with the National Power System (NPS). The project invested by the National Power Transmission Corporation (EVNNPT), and managed by CPMB on behalf of EVNNPT was started for construction on April 09, 2018.
inaugurating song hau 1 thermal power plant

Inaugurating Song Hau 1 Thermal Power Plant

On the afternoon of July 16, in Hau Giang province, Prime Minister Pham Minh Chinh attended the inauguration ceremony of Song Hau 1 Thermal Power Plant, invested by Vietnam National Oil and Gas Group (PVN).
starting out the song hau 1 thermal power plant

Starting out the Song Hau 1 Thermal Power Plant

On May 16, the Prime Minister Nguyen Tan Dung  attended the Ceremony and ordered to start construction of  Song Hau 1 thermal power plant (TPP).
signing epc contract of song hau 1 thermal power plant

Signing EPC Contract of Song Hau 1 thermal power plant

On April 10 afternoon, in Hanoi, the ceremony of EPC contract signing for Song Hau 1 thermal power plant project has taken place between Lilama Corporation and Owner Vietnam Oil and Gas Group
song hau 1 thermal power plant is closely operated in accordance with the new progress milestone

Song Hau 1 thermal power plant is closely operated in accordance with the new progress milestone

Information from Song Hau 1 Petroleum Power Project Management Board (under Vietnam Oil and Gas Group - PVN) said: As of March 15, 2021, the construction of Song Hau 1 thermal power project (TPP – 1200 MW) reaches a cumulative progress about 95.78% including construction of 98.12%, design of 99.91%, procurement of 99.91% and test of 74.85%.
signing the credit and commercial loan contracts for song hau 1 thermal power project

Signing the credit and commercial loan contracts for Song Hau 1 Thermal Power Project

According to information from PVN, on November 23, 2016 there was taken place the ceremony of signing credit contract and commercial loan contract with total value of USD 1.2 billion, between PVN and Korea Export-Import Bank (KEXIM) and Consortium of Nine Foreign Commercial Banks with the clue of Citibank for financing Song Hau 1 Thermal Power Plant (TPP) capacity of (2x600) MW. This TPP is a key project in Power Planning VII invested by PVN and allowed for development by special mechanism application to timely meet high electricity need in southern region in period to 2020.  
epc main contractor lilama has signed contract of construction items for song hau 1 thermal power plant

EPC Main Contractor Lilama has signed contract of construction items for Song Hau 1 thermal power plant

In the afternoon of April 5th, in Hanoi, the contract signing ceremony of performing items of construction & installation for Song Hau 1 thermal power project has taken place between Lilama Corporation (LILAMA) and Petroleum Construction & Installation Corporation (PVC). 
successfully installing the unit1 of song hau 1 thermal power plant

Successfully installing the Unit#1 of Song Hau 1 Thermal Power Plant

In the morning of April 20, 2018, at Song Hau 1 thermal power project (TPP) in Chau Thanh district, Hau Giang province, EPC General Contractor - Lilama Corporation successfully installed the generator of the Unit#1.
Trang tiếp