RSS Feeds for PVC participates in building Nghi Son  Refinery and Petrochemical Complex Project | Tạp chí Năng lượng Việt Nam November 23, 2024 00:26
Vietnam Energy Forum

PVC participates in building Nghi Son Refinery and Petrochemical Complex Project

 - The JGCS general contractor (Affiliation of Contractors: JGC, GS, Chiyoda, SK E&C and Technip, leaded by JGC Japan) has handed CVL 6 (Civil 6) contract package (Nghi Son Refinery and Petrochemical Complex Project) to PetroVietnam Construction Joint-Stock Corporation (PVC). The total value of the package is around VND 500 billion.

The range of package Civi 6

 

According to the agreement signed between JGCS and PVC, PVC will execute the construction for Off-site area (outside the main factory) and a part of the Process area (technological area). The main works of the package include: site preparation, levelling, pile cap settling and concreting, foundation works, roads, construction of reinforced concrete structures...

The package is expected to be complete on November, 2016 and that will be an important contribution in completing the Nghi Son Refinery- Petrochemical complex project on schedule.

Besides, at Nghi Son Refinery and Petrochemical complex project, PVC is now also executing the pakage for first dredging marine works, expected to be complete in 2015.

Nghi Son Refinery and Petrochemical complex project, invested by Nghi Son Refinery and Petrochemical limited company, was commenced by the end of October, 2013. The complex is a Vietnamese national key project on Oil and Gas, and will plays an important role in implementing the socio-economic development strategy and ensuring the energy security of the country.

VietnamEnergy.vn

News

Posted news

[More view]