Doosan Vina completed the super erection of Gemalink’s STS cranes unit 7

 - After nearly eight months since signing the contract to supply two additional super-heavy STS (ship-to-shore) cranes weighing 3,400 tons to the Gemadept - CMA CGM, two STS cranes number 7 and 8 of the Gemalink project have formed after super erection.

Constantly making efforts to overcome all challenges due to the impact of the Covid-19 epidemic, Doosan Vina always proactively takes advantage of opportunities and flexibly adapts to both strengthening the epidemic prevention and ensuring uninterrupted production activities.

“For two additional super heavy cranes No.7 and 8 of the Gemalink RMQC project, after signing the order in March 2021, we started production in April and have completed 100% of fabrication and about 90% of the erection. Currently, we along with workers of subcontractors have just completed the Super Erection of Unit 7 and are preparing to step toward to the electrical system connection, elevator alignment, gantry, and cable reel phases." Yoon Young Sang, Team Leader of Erection, Doosan Vina said.

The Super Erection is the most important stage of the crane erection. It took about 04 hours to complete the installation of the winch system to winch and pull large parts such as Boom & Girder, Top Beam, Top Leg, Machinery House to assemble, connect with 4 legs to form a complete RMQC crane, then switch to the stages of electrical connection, installation of the elevator system, line check, power on, and operation test.

Along with the erection of unit 7, unit 8 of this project is also in the electrical connection for the Machinery House and preparing necessary things for the Super Erection.

By design, each of the eight STS cranes of the Gemalink project is 93m high, 150m long, 27m wide and weighs more than 1,700 tons. It can reach up to 70 meters into the sea (equivalent to 24+2 rows of containers) and could lift the project cargo of 65 tons from large mother vessels up to 200,000 DWT. With a such big size, the in-charge engineers must calculate and check each parameter carefully to meet the technical requirements, accuracy, and safety in each production step.

As planned, these two super-heavy cranes will be electrically connected, commissioned in mid-November, and handed over to the customer as per the contract term. Once put into operation, they along with six STS cranes (supplied by Doosan Vina in 2020) will contribute to meeting the needs of improving loading and unloading efficiency, exploiting the full design of 1.5 million TEU of phase 1 from Y2022 at the Gemalink port, Gemadept - CMA CGM.

Doosan Vina

Doosan Vina is a high-tech industrial complex in the Dung Quat Economic Zone of Central Vietnam’s Quang Ngai Province employing 2,000 Vietnamese. The company supplies the mega infrastructure products that make modern life a reality. Doosan Vina’s products include: Boilers for thermal power plants, Desalination plants the size of a football pitch that turn seawater into fresh, Material Handling Systems like cranes that are the heart of logistics at ports around the world, Modularization and Structural Steel for refineries, buildings and infrastructure developments. To date the company has exported products valued at $2.4 billion.

The Doosan Group

The Doosan Group is a global multinational focusing on Power, Water and other infrastructure developments worldwide. The company is headquartered in Seoul, South Korea, has operations in 38 countries, over 42,600 employees and $22 billion in annual revenue.

Some of the photos:

Doosan Vina completed the super erection of Gemalink’s STS cranes unit 7

Doosan Vina completed the super erection of Gemalink’s STS cranes unit 7

Doosan Vina completed the super erection of Gemalink’s STS cranes unit 7
VietnamEnergy.vn

News

Posted news

[More view]