Investment Policy and Investor Approved for Hong Loc Solar Power Plant Project in Ha Tinh Province

 - According to information from the People’s Committee of Ha Tinh Province, the provincial authority has issued a decision approving the investment policy for the Hong Loc Solar Power Plant Project and approving HLT Green Technology Joint Stock Company as the investor.

Under Decision No. 35/QĐ-UBND dated September 14, 2026, issued by the People’s Committee of Ha Tinh Province, the investment policy for the Hong Loc Solar Power Plant Project was approved and HLT Green Technology Joint Stock Company was approved as the investor. The project has the following key details:

  • The project will be implemented in Hong Loc Commune.

  • The project is expected to use approximately 55.5 hectares of land, including the solar power plant area, auxiliary facilities, grid connection facilities, and the expansion of a feeder bay at the Can Loc 110 kV Substation.

  • The project will have a designed capacity of 49 MW, with an expected average annual electricity output of approximately 68.62 million kWh.

  • The total investment capital is estimated at VND 763.312 billion.

  • The project will have an operating term of 50 years, starting from the date on which the State allocates or leases the land.

  • The project will have an implementation period of 12 months from the date on which the land is allocated or leased.

  • The project is expected to be completed in Q4 2027.

To ensure that the project is implemented in accordance with regulations and on schedule, the People’s Committee of Ha Tinh Province has requested the following:

Requirements for the investor

First, before the State allocates or leases the land, the investor must complete the procedures for making a security deposit or implementing other measures to secure project implementation in accordance with investment laws, within a period of no more than six months from the effective date of the Decision.

Second, the investor must complete all required documents and procedures and commence construction of the project within six months from the effective date of the Decision. Construction of project components may only begin after all required procedures relating to investment, land, construction, environmental protection, forestry, fire prevention and firefighting, electricity and other relevant matters have been fully completed.

Third, during project implementation, the project must ensure that it does not affect irrigation works, drainage systems, protection corridors of technical infrastructure facilities, national defense and security facilities, or other lawful structures.

Fourth, the investor must implement measures to protect the environment and ensure effective drainage, prioritize the use of local labor, and coordinate with local authorities in communication activities to build consensus among residents.

Requirements for the Hong Loc Commune People’s Committee

The Hong Loc Commune People’s Committee will lead and coordinate with the investor and relevant agencies and organizations to complete compensation and site clearance and allocate the land to the investor within seven months of the Decision's issuance. It will also monitor, urge, inspect, and supervise project implementation./.