RSS Feeds for Approving adjustment of investment policy and the investor for Huong Linh 3 WPP | Tạp chí Năng lượng Việt Nam November 22, 2024 00:08
Vietnam Energy Forum

Approving adjustment of investment policy and the investor for Huong Linh 3 WPP

 - Chairman of Quang Tri Provincial People's Committee (PPC) Vo Van Hung has just signed Decision No. 756/QD-UBND approving the adjustment of investment policy and the investor of the Huong Linh 3 wind power project.

According to the Decision, the investment policy of Huong Linh 3 Wind Power Project is the first time approved by Quang Tri PPC for the Huong Linh 3 Wind Power Joint Stock Company (headquartered in Cooc village, Huong Linh commune, Huong Hoa district) as the investor (Decision No. 781/QD-UBND dated April 9, 2019).

The Huong Linh 3 wind power project with a total capacity of 30 MW, average generation of 123.329 GWh/year is designed with 9 wind turbines with each capacity from 3.3 to 3.465 MW. The project is implemented on 8 ha in Huong Linh commune, Huong Hoa district (excluding land area for the foundations of the connecting grid to the national power system). The total project investment capital is more than 1,530 billion VND.

According to the project progress in the decision on approving the investment policy, from March 2019 to May 2019, establishing technical design, construction drawing. In December 2020, implementing adjustments, connection and power generation.

However, in mid-2020, Tan Hoan Cau Joint Stock Corporation sent a document to propose adjustment of investment projects. So on October 13, 2020, Quang Tri PPC issued Decision No. 2946/QD-UBND on approving the adjustment of the project investment policy.

At this adjustment time, the investment capital of this Huong Linh 3 wind power project was adjusted down from 1,530 to 1,118 billion VND as an original plan.

Then, on March 10, 2022, Quang Tri PPC issued Decision No. 756/QD-UBND on approving the adjustment of the project investment policy and handing Huong Linh 3 Wind Power Joint Stock Company as the project investor.

In this Decision, the land area for the project is adjusted from 8.0 to 9.02 ha and the progress schedule of testing, correcting and connecting activities will be carried out until September 2022.

VietnamEnergy.vn

News

Posted news

[More view]