RSS Feeds for Staring construction of Phuoc An 220 kV switch substation | Tạp chí Năng lượng Việt Nam March 29, 2024 17:54
Vietnam Energy Forum

Staring construction of Phuoc An 220 kV switch substation

 - On Oct. 17 2016, the Management Board of the Central Power Projects (CPMB) carried out ground breaking the contract package No 8 for constructing switch substation and a turnout line under Phuoc An 220 kV switch substation project (in Dai Hoi village, Phuoc An commune, Tuy Phuoc district, Binh Dinh province).

This project aims to strengthen interconnection of power grids in the region and prepare reserve land for Phuoc An 220/110/22 kV transformer substation with a capacity of 2x250 MVA to meet the electricity demand growth and socio-economic development of Binh Dinh province.

The total investment of the project estimated VND 162.72 billion including WB TEP loan and EVN NPT equity capital.

This project invested by EVN NPT and managed by  CPMB on behalf of EVN NPT expects to be put into operation in IV quarter, 2017.