Announcing the detailed planning for the Solar Power Project of EVNCPC
08:42 | 20/09/2018
The boundary of detailed construction planning in 1/500 scale of EVNCPC
The total area of project planning zone is estimated around 70.52 ha and the project site is located on a delta area before and between the mountains.
According to CPCCREB, up to now, the project has obtained the investment policy approval by Khanh Hoa Provincial People’s Committee (PPC) and the certificate of investment registration by Khanh Hoa Department of Planning and Investment (DPI).
The environmental impact assessment document for the project has also been approved by Khanh Hoa PPC through Decision No. 1917 / QD-UBND dated 4/7/2018.
CPCCREB has also completed the appraisal and approval of the technical design and drawings for 110kV line and transformer substation, and selecting the contractors for material supply and construction.
As planned, the project will be started for construction in September 2018, checked before acceptance and put into operation in quarter II of 2019.
The project including the solar power plant with a capacity of 50 MW, step-up 22/110kV transformer substation with a capacity of 63 MVA and a 110kV line for connecting the solar power plant with the national power system at 110kV Cam Ranh transformer substation with a length of 14 km invested by EVNCPC.