Approving the investment policy for the KN Ialy Kon Tum solar power project
09:09 | 12/04/2021
The KN Ialy Kon Tum solar power project with a capacity of 200 MWp is developed on an area of 233 ha of Ialy hydropower plant reservoir in Ya Tang commune and Ya Ly commune, Sa Thay district, Kon Tum province.
The project expects to be started for construction in December of 2021, completed and put into operation in December of 2024. The operation duration of the project will be 50 years from the date of approving the investment policy.
The total investment level of the project is estimated at 4,121 billion VND, including 620 billion (15% of total investment) from the investor and a 3501billion (85% of total investment) from mobilized capital
The project is subject to approving the investment policy and investor without bidding the land use right and the investor selection.