Powering 220 kV transformer substation for BIM Wind Power Project
12:02 | 17/08/2021
The acceptance committee prepares for the energizing operation. |
The 220 kV transformer substation of the BIM wind power project includes a transformer with six 220 kV feeders for connecting the BIM power farm with an imminent capacity of 88 MW and a standby transformer with the voltage of 33/33/220 kV and a capacity of 200 MVA.
In this project, the PECC1 has provided the following services:
1/ Surveying for making the technical design and design of construction drawings of 220 kV transformer substation and transmission lines for BIM wind power farm connection
2/ Making the technical design, design of construction drawings for the 220 kV transformer substation.
3/ Making the technical design and design of construction drawings for the 220 kV double connecting line with a length of 3 km, and section of 240 mm2 (suspending one circuit in the first phase).
4/ Extending D09 feeder at Quan The 220 kV transformer substation.
5/ Making technical design and design for 35 kV cables connecting wind turbines and for grounding turbines.
6/ making designs of construction drawings for the operating house and warehouse.
Distribution yard 220 kV |
With the high responsive spirit and experience, the engineers of the Transformer Substation Consulting Center of PECC1 have successfully completed the assigned works with suitable design solutions and reasonable construction costs.